Upper-Wall Schedule

2005
Tuesday, April 12

4:30pm
Found out from Tim what the upcoming schedule is for the Upper-walls and house structure.

Friday 4/15 - scheduled for the Deck (or flooring). This will be where the AdvanTech Flooring will come in. Also whatever supports they'll need to do that will also be assembled.

Early next week - upper walls will be assembled. By upper walls, I mean the actual house walls that Barden is constructing in their factory.

Wednesday 4/20 - scheduled for the trusses, which are basically the supports for the house/roof.