Roofing

2005
Monday, April 25
8pm

I didn't think that they would do any work today, due to the crapy rainy day, but I guess it didn't stop them from started on installing the roof. Currently they're installing plywood over the trusses and should be finished by Thursday, if the weather cooperates.












With half the plywood installed, it gave a better idea of what kind of light we'll be getting in the house. I think that deck door was a perfect request for the kitchen. That, plus the window on the garage side, will give the kitchen awesome light.


Even though the living/dinning and kitchen makes for a long room, the nice large 6 foot window in front, matched with the windows in the kitchen, should give the house some decent light.




Upcoming Schedule -
We'll be meeting with Mike and the forman at noon on Thursday on site and go over things and discuss what's next. And now that the framework is up, we can contact the kitchen place and order everything. We're told it'll take about 2 or so weeks after that for ordering time.